Billing Migration Project from Legacy Application to SAP CR&B

PROJECT HIGHLIGHTS

  • Large 1.5 year Billing Migration project from legacy systems to SAP
  • Maximize software maintenance and production support by collapsing multiple IT support teams
  • Complex landscape environment

 

CLIENT PROFILE

Fortune 500 Utility Electric And Gas Distribution Provider Delivering Energy To 2 Million Plus Metered Customers

 

OBJECTIVES

  • Unit Testing (12 Weeks)
  • Functional Acceptance Testing (End-to-end Process)
  • User Acceptance Testing(24 Weeks Of Uat)
  • Integration Testing (24 Weeks - 3 Cycles)
  • Regression/swat Testing (6 Weeks)
  • Performance/stress (2 Weeks)
  • Bw (Queries &  Reports)
  • C&i Billing, Finance
  • Central Metering
  • Electric Mgt. Office
  • Market Transactions
  • Streetlights

 

IMPLEMENTATION HIGHLIGHTS

  • Followed Testing Methodology and processes & gate review/approvals
  • 880+ test cases/templates are created and reusable testing inventory
  • Testing inventory used for future projects
  • Successful go-live in 2015 with minimal production post go-live defects